Consultation, General Electrical Maintenance Of Outdoor Ground Mounted Transformer Substation at Irvine’s Tanzania Industrial Area Bagamoyo.
Project Summary
CLIENT
Irvine’s Tanzania Ltd
LOCATION
Kerege, Bagamoyo
FACILITY TYPE
Outdoor Transformer Substation
START - FINISH | DURATION
2022, Completed
CONTRACTOR
Ngilisho Electrical Contractors
SERVICE | PROJECT SIZE
Consultation, General Maintenance of 1000KVA ,33/0.4KV transformer, maintenance and general services of switchgear/ circuit breaker, transformer oil filtration, oil breakdown voltage test (dielectric strength test) and others in order to ensure power availability and better performance of the transformer.
PROJECT DETAILS
Maintenance of 1000KVA ,33/0.4KV transformer which included visual inspection, cleaning, recording & tightening of terminals, check & test Buchholz relay operation & pressure release device, carry-out winding resistance, earth resistance & insulation resistance measurement test, silica-gel replacement, check Oil leakage along all welded joint, gasket joint and plugs, bushing gaskets replacement, transformer oil filtration, oil breakdown voltage test (dielectric strength test) and others in order to ensure power availability and better performance and lifespan of the transformer.